TeraWulf Inc. Q2 FY2026 Earnings Call
· Earnings call transcript and AI-powered summary
Company: TeraWulf Inc.
Period: Second Quarter 2026 (ended June 30, 2026)
Executives on Call: Paul Prager (Chairman & CEO), Nazar Khan (CTO), Patrick Fleury (CFO), John Larkin (SVP & Director of IR)
Key Highlights
- Delivered CB-3 at Lake Mariner, bringing total operating critical IT capacity to 102 MW and generating lease revenue starting late June/early July 2026.
- Executed 20-year lease with Anthropic for ~401 MW at Justified Data campus (Hawesville, KY), representing ~$19 billion in contracted revenue over the initial term.
- Acquired Muskie Data campus in Eastern Kentucky (1 GW electric service agreement, potential expansion to 2 GW); utility-supported development with Kentucky Power (AEP).
- Agreed to sell 50.1% interest in Abernathy JV for ~$530 million (20% IRR on initial investment).
- Received FERC approval for Morgantown site acquisition (Chesapeake, MD); ~210 MW existing generation with potential for up to 1 GW data center capacity.
- Reaffirmed annual contracting target of 250-500 MW of critical IT capacity.
Financial Performance (Q2 2026 vs Q1 2026)
- Total Revenue: $44.8 million (up from $34.0 million), driven by additional HPC capacity online.
- HPC Lease Revenue: $31.9 million (up 52% from $21.0 million), representing 71% of total revenue.
Continue Reading
Unlock the full AI-powered summary with key highlights, financial performance, and analyst Q&A.
Upgrade to ProfessionalContinue Reading
Unlock the full earnings call transcript with speaker labels and formatted dialogue.
Upgrade to Professional