TeraWulf Inc. Q3 FY2026 Earnings Call
· Earnings call transcript and AI-powered summary
Company: TeraWulf (Energy Infrastructure / Data Center Developer)
Period: Third Quarter ended September 30, 2026 (compared primarily to Q2 2026)
Key Highlights & Milestones
- Secured Google's credit support for financing of $19 billion, 20-year lease with Anthropic at Justified Data Campus in Hawesville, KY.
- Entered definitive EPC agreement with Fluor for full engineering, procurement, construction, testing, and commissioning of all 3 data center buildings at Justified.
- Construction at Justified underway (pilings started); phased ready-for-service deliveries targeted late 2027 through Q2 2028.
- Lake Mariner campus (Wolfe Compute): CB-3 fully online and generating revenue; CB-4 first two data halls nearing commercial operation; CB-5 commissioning starting soon for Q1 2026 phased delivery.
- By end of Q1 2027, expect ~half of contracted critical IT capacity operating with ~$700 million annualized run-rate leasing revenue.
Project Updates
- Justified (Hawesville, KY): $19B contracted revenue with Anthropic; Google investment-grade credit backstop; expected costs $10-12M per critical IT MW. Equity already contributed (~$550M); path to project-level debt financing.